At the end of week five we had our pre-drywall meeting.  Everything in the house looked great except for the rain coming in through the roof and one of the walls.  The roofer failed to install the roof vents in the morning room so the rain was coming in.  Somehow the rain was getting behind the house wrap and seeping through a wall in the kitchen.  The project manager assured us that the insulation would not be installed until the wall had dried.

During week six the house was insulated, the drywall was hung, and the garage door was installed.  